Case Studies - Birmingham Airport

Birmingham Airport Logo

Birmingham Airport

 

A Technical Energy Survey of the Baggage Handling area at Birmingham Airport revealed that there were potential savings by modifying the existing BMS (Building Management System) to return 19% in electricity & gas savings.

 

Electrical Energy Cost:
£12,500.00
Total Gas Cost:
£3,000.00
   
Total Savings per annum:
£3,000.00

(19% of Total saved)

 
BMS Energy Project Works Cost:
£1,500.00
   
Pay-back period:
0.5  Year
Energy saved per annum:
38  MWH
Tons of Carbon saved:
16  Tonnes

 

BMS software re-written to allow the plant to operate between selected high/low temperatures only. Demma Integration software logging conditions, training provided for technical Engineers.

 (On going savings of £3.0K every year & increasing)